Project Schedule Performance of IFI Financed Public Projects: Evidence from Uzbekistan

https://doi.org/10.35912/gabs.v2i3.3945
12 Feb 2026

Abstract

Purpose: This study aims to assess the schedule performance of public-sector investment projects financed by major international financial institutions (IFIs) in Uzbekistan, focusing on the differences in implementation timelines based on funding institutions, project size, and sectoral characteristics.

Research methodology: Using publicly available data on IFI-financed projects approved between 2010 and 2024, this study evaluates project performance through planned versus actual implementation duration, time overruns, and formal project extensions. Descriptive statistics, non-parametric tests, and logistic regression models were employed to analyze the probability of schedule extensions while controlling for project size, sector, and approval year.

Results: The analysis revealed significant variations in schedule performance across IFIs, with larger infrastructure projects having a higher likelihood of delays.

Conclusions: The findings suggest that institutional governance and project monitoring play crucial roles in the management of project time.

Limitations: The study relies on publicly available data, which may not capture all project variables, and is limited to projects financed by specific IFIs.

Contributions: This research contributes to the understanding of project schedule performance in transition economies and highlights the value of using open, transparent data for comparative performance studies, providing policy insights for improving schedule risk management in similar contexts.

Keywords

International Financial Institutions Project Schedule Performance Public-Sector Investment Projects Teaching Hospita Time Overruns Uzbekistan Open Data

How to Cite

Samira, Y. ., & Mirkhojidin, M. . (2026). Project Schedule Performance of IFI Financed Public Projects: Evidence from Uzbekistan. Global Academy of Business Studies, 2(3), 217–229. https://doi.org/10.35912/gabs.v2i3.3945

References

  1. Abdelalim, A. M., Salem, M., Salem, M., Al-Adwani, M., & Tantawy, M. (2024). An analysis of factors contributing to cost overruns in the global construction industry. Buildings, 15(1), 18. doi:https://doi.org/10.3390/buildings15010018
  2. Amin, H., Malik, M., & Scheepers, H. (2024). An agency theory unpacking of how monitoring and evaluation affect international development project impact. International journal of project management, 42(8), 1-11. doi:https://doi.org/10.1016/j.ijproman.2024.102654
  3. Antoniou, F., & Tsavlidou, E. (2025). Ranking public infrastructure project success using multi-criteria analysis. Buildings, 15(16), 1-24. doi:https://doi.org/10.3390/buildings15162807
  4. Ashton, L., Friedman, J., Goldemberg, D., Hussain, M. Z., Kenyon, T., Khan, A., & Zhou, M. (2023). A puzzle with missing pieces: explaining the effectiveness of World Bank development projects. The World Bank Research Observer, 38(1), 115-146. doi:https://doi.org/10.1093/wbro/lkac005
  5. Asiedu, R. O., & Adaku, E. (2020). Cost overruns of public sector construction projects: a developing country perspective. International Journal of Managing Projects in Business, 13(1), 66-84. doi:https://doi.org/10.1108/IJMPB-09-2018-0177
  6. Brookes, N. J., & Locatelli, G. (2015). Power plants as megaprojects: Using empirics to shape policy, planning, and construction management. Utilities Policy, 36, 57-66. doi:https://doi.org/10.1016/j.jup.2015.09.005
  7. Bustami, K., & Saifrizal, M. (2025). Project Performance in Infrastructure Development: Analysis of Time and Quality Control Against Budget Allocation. Journal Informatic, Education and Management (JIEM), 7(2), 527-535. doi:https://doi.org/10.61992/jiem.v7i2.169
  8. Chasanah, N., Gunawan, I., & Baroudi, B. (2024). International development project success: A literature review. Journal of International Development, 36(1), 146-171. doi:https://doi.org/10.1002/jid.3809
  9. Figueroa, C., Huppi, M., Riveros, L., Vargas, L., Garay, I., Wong, M., . . . Motta, M. (2025). Comparative Analysis of Project Development Effectiveness Management Tools for Sovereign Guaranteed Operations of the AfDB, ADB, IDB, IFAD, and WB.
  10. Flyvbjerg, B. (2014). What you should know about megaprojects and why: An overview. Project management journal, 45(2), 6-19. doi:https://doi.org/10.1002/pmj.21409
  11. Gómez-Cabrera, A., Cortés, S., Rojas, J., Sánchez, O., & Torres, A. (2025). Data-driven analysis of contracting process impact on schedule and cost performance in road infrastructure projects in Colombia. Buildings, 15(20), 3739. doi:https://doi.org/10.3390/buildings15203739
  12. Ika, L. A., & Donnelly, J. (2017). Success conditions for international development capacity building projects. International journal of project management, 35(1), 44-63. doi:https://doi.org/10.1016/j.ijproman.2016.10.005
  13. Ivi?, I., & Ceri?, A. (2023). Risks caused by information asymmetry in construction projects: A systematic literature review. Sustainability, 15(13), 9979. doi:https://doi.org/10.3390/su15139979
  14. Kele?, A. E., Gülek, G. G., & Górecki, J. (2025). Use of project management knowledge areas in civil infrastructure projects: Implications for sustainability assessment and risk analysis. Sustainability, 17(20), 9129. doi:https://doi.org/10.3390/su17209129
  15. Kenjabaev, A., & Sadriddinov, B. (2025). Project Management Development Trends In Uzbekistan. TLEP–International Journal of Multidiscipline, 2(4), 277-283.
  16. Kilani, Q., Harahsheh, F., Najdawi, S., Khzouz, A., Al-Badaineh, G., Abualfalayeh, G., & Hanandeh, A. (2024). Evaluating the impact of scope, time, cost, and quality management on project performance and business overall performance in Jordanian financial sector. Journal of Project Management (Canada), 9(4), 301-310. doi:https://doi.org/10.5267/j.jpm.2024.9.003
  17. Koirala, M. P., & Shahi, R. S. (2024). Examining the causes and effects of time overruns in construction projects promoted by rural municipalities in Nepal. Evaluation and Program Planning, 105, 1-11. doi:https://doi.org/10.1016/j.evalprogplan.2024.102436
  18. Liu, Y., Mao, S., Zhang, B., Xu, Q., & Zhu, Q. (2025a). Relational governance and project performance: Unveiling the mediating role of organizational resilience. Buildings, 15(10), 1585. doi:https://doi.org/10.3390/buildings15101585
  19. Liu, Y., Mao, S., Zhang, B., Xu, Q., & Zhu, Q. (2025b). Relational governance and project performance: Unveiling the mediating role of organizational resilience. Buildings, 15(10), 2-17. doi:https://doi.org/10.3390/buildings15101585
  20. Mekonen, E. K., Shedaga, T., & Sahle, M. (2025). Determinants of construction project delay and its effect on project beneficiaries: evidence from the Gurage Zone, Ethiopia. Discover Civil Engineering, 2(1), 1-9. doi:https://doi.org/10.21203/rs.3.rs-3753873/v1
  21. Melaku Belay, S., Tilahun, S., Yehualaw, M., Matos, J., Sousa, H., & Workneh, E. T. (2021). Analysis of cost overrun and schedule delays of infrastructure projects in low income economies: case studies in Ethiopia. Advances in Civil Engineering, 2021(1), 4991204. doi:https://doi.org/10.1155/2021/4991204
  22. Omilovna, K. N. (2024). Development of investment activities in the automobile industry of Uzbekistan in the conditions of the digital economy. Global Academy of Business Studies(GABS), 1(2), 135-145. doi:https://doi.org/10.35912/gabs.v1i2.3469
  23. Orya, F., & Calahorra-Jimenez, M. (2025). Delays in Infrastructure Projects: Main Reasons in the Design, Procurement, and Construction Phases. Public Works Management & Policy, 30(2), 261-280. doi:https://doi.org/10.1177/1087724X241308310
  24. Ottaviani, F. M., De Marco, A., Narbaev, T., & Rebuglio, M. (2024). Improving project estimates at completion through progress-based performance factors. Buildings, 14(3), 643. doi:https://doi.org/10.3390/buildings14030643
  25. Pambudi, H. J. (2025). The effect of risk management, schedule performance, and cost efficiency on the feasibility of infrastructure project investment. Eduvest - Journal of Universal Studies, 5(9), 11392-11405. doi:https://doi.org/10.59188/eduvest.v5i9.52143
  26. Park, J. E. (2021). Schedule delays of major projects: what should we do about it? Transport Reviews, 41(6), 814-832. doi:https://doi.org/10.1080/01441647.2021.1915897
  27. Precious, D. (2025). Infrastructure Project cost overrun and schedule delay in Ghana: Is it an issue of resource misallocation or financial constraints? Project Leadership and Society, 6, 100188. doi:https://doi.org/10.1016/j.plas.2025.100188
  28. Rodríguez Estévez, D., & Arce Ruíz, R. M. (2024). Assessing Multilateral Development Bank ESG Safeguard Integration with International Sustainability Ratings. Sustainability, 16(9), 3789. doi:https://doi.org/10.3390/su16093789
  29. Royan, M., & Assa, A. F. (2025). The effect of quality of work life and organizational citizenship behavior on employee performance: Mediated by work motivation. Global Academy of Business Studies(GABS), 2(2), 151-163. doi:https://doi.org/10.35912/gabs.v2i2.3671
  30. Sharuddin, N. M., Azman, M. A., Abdul Samad, Z., & Mohd Rodzi, R. (2024). Relationship between schedule delay factors and project performance in civil engineering works. Built Environment Journal, 21, 23-36. doi:https://doi.org/10.24191/bej.v21iSpecial
  31. Sherzod, Y. (2025). Enhancing the institutional framework of relations between the republic of Uzbekistan and international financial institutions. Central Asian Journal of Innovations on Tourism Management and Finance, 6(4), 1455-1460. doi:https://doi.org/10.51699/cajitmf.v6i4.1015
  32. Solís-Carcaño, R. G., Corona-Suárez, G. A., & García-Ibarra, A. J. (2015). The use of project time management processes and the schedule performance of construction projects in Mexico. Journal of Construction Engineering, 2015(1), 868479. doi:https://doi.org/10.1155/2015/868479
  33. Ugochukwu, A. I., & Phillips, P. W. (2024). Open data ownership and sharing: Challenges and opportunities for application of FAIR principles and a checklist for data managers. Journal of Agriculture and Food Research, 16, 1-9. doi:https://doi.org/10.1016/j.jafr.2024.101157
  34. Wang, Y., & Levinson, D. (2023). The accuracy of benefit-cost analysis for transport projects supported by the Asian Development Bank. Asian Transport Studies, 9, 100104. doi:https://doi.org/10.1016/j.eastsj.2023.100104
  35. Weng, X., Yuan, C., Li, X., & Li, H. (2024). Research on the construction of a risk assessment indicator system for transportation infrastructure investment under public–private partnership model. Buildings, 14(6), 1679. doi:https://doi.org/10.3390/su17209129
  36. Yi, B., & Nie, N. L. S. (2024). Effects of contractual and relational governance on project performance: The role of BIM Application Level. Buildings, 14(10), 3185. doi:https://doi.org/10.3390/buildings14103185
  37. Zhao, J., Gou, Y., & Li, W. (2019). A new model of multilateral development bank: a comparative study of road projects by the AIIB and ADB. Journal of Chinese Political Science, 24(2), 267-288. doi:https://doi.org/10.1007/s11366-018-9580-5