Solutions for the concrete readymix supply shortage on projects in the New Capital (IKN) of Indonesia

Published: Oct 14, 2025

Abstract:

Purpose: This study aimed to develop a comprehensive conceptual framework representing all aspects of the Readymix Concrete Supply Chain, including Environment, Product, Method, Supply Chain, Time, and Finance. It seeks to identify the main probable causes of operational issues using the Kepner-Tregoe analysis to support effective decision-making.

Methodology: The Kepner-Tregoe analysis was applied to evaluate the situation and identify the root causes. SWOT analysis was then used to analyze the internal and external factors affecting company performance and generate strategic alternatives. Subject Matter Experts (SMEs) conducted pairwise comparisons based on five solution criteria: Cost, Flexibility & Adaptability, Schedule, Product Quality, and Supply Chain Reliability. The Analytical Hierarchy Process (AHP) was used to prioritize three alternative solutions for PT.

Results: Findings indicate that constructing a new batching plant ranks as the top alternative, with a priority score of 50.3%, aligning strongly with the five key criteria and demonstrating high feasibility for implementation.

Conclusion: The decision to establish a new batching plant can improve supply chain performance, provided that risk mitigation, budget planning, and site mapping are completed before the execution.

Limitations: The study is limited by its reliance on expert judgment and single-company analysis, which may restrict generalizability.

Contribution: This research offers a practical decision-making framework that integrates the Kepner-Tregoe, SWOT, and AHP methods to optimize operational efficiency and strategic planning in the concrete supply chain sector.

Keywords:
1. Analytical Hierarchy Process
2. Kepner-Tregoe Problem Analysis
3. Readymix Concrete Supply
4. SWOT Analysis
Authors:
1 . Pandit Purnajuara
2 . Mursyid Hasan Basri
How to Cite
Purnajuara, P. ., & Basri, M. H. . (2025). Solutions for the concrete readymix supply shortage on projects in the New Capital (IKN) of Indonesia. Global Academy of Multidisciplinary Studies, 1(4), 275–294. https://doi.org/10.35912/gams.v1i4.3564

Downloads

Download data is not yet available.
Issue & Section
References

    Anirwan, A., Aljurida, A., & Baharuddin, T. (2024). Developing a New Capital City (IKN) In Indonesia: A Thematic Analysis. Policy & Governance Review, 8, 1-18. doi:https://doi.org/10.30589/pgr.v8i1.863

    Bazyar, A., & Abbasi, M. (2025). Multi-objective planning for a multi-echelon supply chain using parameter-tuned meta-heuristics. Annals of Management and Organization Research, 7(1), 45-65. doi:https://doi.org/10.35912/amor.v7i1.2542

    Donald, J. B., David, J. C., M Bixby, C., & John, C. B. (2020). Supply chain logistics management: McGraw-Hill Education.

    Effendi, Y. M., & Siallagan, M. P. S. (2025). Prioritizing the product development roadmap of Zains SAAS using Analytical Hierarchy Process (AHP). International Journal of Accounting and Management Information Systems, 1(2), 121-141. doi:https://doi.org/10.35912/ijamis.v1i2.3042

    Groot, W. (2021). Root cause analysis–what do we know? Maandblad voor accountancy en bedrijfseconomie, 95(1/2), 87-93. doi:https://doi.org/10.5117/mab.95.60778

    Gurl, E. (2017). SWOT analysis: A theoretical review.

    Hussain, A. (2024). The Tale of Technology: A Guide to Understanding Technology Business in the 21st Century: Notion Press.

    Kepner, C. H., & Tregoe, B. B. (1997). The New Rational Manager Princeton Research Press.

    Khanam, M. (2023). Subject Matter Expert (SME) Management Strategy for Multi-Criteria Decision Making (MCDM): A Case Study of Hierarchical Decision Model (HDM). Paper presented at the 2023 Portland International Conference on Management of Engineering and Technology (PICMET).

    Kristamuljana, S. (1998). Landasan Teori Metode Kasus untuk Pengembangan Manajer yang Rasional. Paper presented at the Forum Manajemen.

    Kurnia, G., Johanes, H., Hidayat, D., Rozha, A., Zahvira, M., & Sukarno, I. (2020). Improving Airport On-Time Performance Using Kepner-Tregoe Problem-Solving Approaches. Jurnal Teknologia, 3(1), 493086.

    Luft, J. A., Jeong, S., Idsardi, R., & Gardner, G. (2022). Literature reviews, theoretical frameworks, and conceptual frameworks: An introduction for new biology education researchers. CBE—Life Sciences Education, 21(3), rm33. doi:https://doi.org/10.1187/cbe.21-05-0134

    Mahgoub, M., Hussein, M., & Mousa, A. (2024). Extended discharge time of ready-mixed concrete: Myth or necessity? Construction and Building Materials, 437, 136913. doi:https://doi.org/10.1016/j.conbuildmat.2024.136913

    Mann, W. C., & Lane, J., P. (1995). Technology and Disability. 4(2).

    Nson, Y. D. (2024). Management by walking about in achieving organizational excellence: The role of total quality management. Annals of Human Resource Management Research, 4(2), 111-126. doi:https://doi.org/10.35912/ahrmr.v4i2.2408

    Nurokhman, N., Suharyanto, I., & Rochmawati, U. (2021). Evaluasi Mutu Beton Dari Berbagai Ready Mix Pada Gedung Parkir Yogyakarta International Airport. CivETech, 3(2), 55-65. doi:https://doi.org/10.47200/civetech.v3i2.1058

    Padmowati, R. d. L. E. (2009). Pengukuran index konsistensi dalam proses pengambilan keputusan menggunakan metode AHP. Paper presented at the Seminar Nasional Informatika (SEMNASIF).

    Palcic, I., & Lalic, B. (2009). Analytical Hierarchy Process as a tool for selecting and evaluating projects. International Journal of Simulation Modelling (IJSIMM), 8(1). doi:https://doi.org/10.2507/IJSIMM08(1)2.112

    Pottonen, J. (2023). Utilization of The 8d Quality Tool in Solving The Quality Problems in John Crane Nordic Units.

    Quesada, H., Gazo, R., & Sanchez, S. (2012). Critical factors affecting supply chain management: A case study in the US pallet industry. Pathways to supply chain excellence, 33-56.

    Ravitch, S. M., & Riggan, M. (2016). Reason & rigor: How conceptual frameworks guide research: Sage publications.

    Saaty, T. L., & Vargas, L. G. (2012). Models, methods, concepts & applications of the analytic hierarchy process (Vol. 175): Springer Science & Business Media.

    Sabbaghi, A., & Vaidyanathan, G. (2004). SWOT analysis and theory of constraint in information technology projects. Information systems education journal, 2(23), 1-19.

    Simchi-Levi, D., Kaminsky, P., & Simchi-Levi, E. (2004). Managing the supply chain: the definitive guide for the business professional: McGraw-Hill.

    Stemmler, L. (2002). The role of finance in supply chain management. Paper presented at the Cost management in supply chains.

    Steward, M. D., Wu, Z., & Hartley, J. L. (2010). Exploring supply managers' intrapreneurial ability and relationship quality. Journal of Business-to-Business Marketing, 17(2), 127-148. doi:https://doi.org/10.1080/10517120903407857

    Westland, J. (2006). The project management life cycle: a complete step-by-step methodology for initiating, planning, executing & closing a project successfully: Kogan Page Limited.

  1. Anirwan, A., Aljurida, A., & Baharuddin, T. (2024). Developing a New Capital City (IKN) In Indonesia: A Thematic Analysis. Policy & Governance Review, 8, 1-18. doi:https://doi.org/10.30589/pgr.v8i1.863
  2. Bazyar, A., & Abbasi, M. (2025). Multi-objective planning for a multi-echelon supply chain using parameter-tuned meta-heuristics. Annals of Management and Organization Research, 7(1), 45-65. doi:https://doi.org/10.35912/amor.v7i1.2542
  3. Donald, J. B., David, J. C., M Bixby, C., & John, C. B. (2020). Supply chain logistics management: McGraw-Hill Education.
  4. Effendi, Y. M., & Siallagan, M. P. S. (2025). Prioritizing the product development roadmap of Zains SAAS using Analytical Hierarchy Process (AHP). International Journal of Accounting and Management Information Systems, 1(2), 121-141. doi:https://doi.org/10.35912/ijamis.v1i2.3042
  5. Groot, W. (2021). Root cause analysis–what do we know? Maandblad voor accountancy en bedrijfseconomie, 95(1/2), 87-93. doi:https://doi.org/10.5117/mab.95.60778
  6. Gurl, E. (2017). SWOT analysis: A theoretical review.
  7. Hussain, A. (2024). The Tale of Technology: A Guide to Understanding Technology Business in the 21st Century: Notion Press.
  8. Kepner, C. H., & Tregoe, B. B. (1997). The New Rational Manager Princeton Research Press.
  9. Khanam, M. (2023). Subject Matter Expert (SME) Management Strategy for Multi-Criteria Decision Making (MCDM): A Case Study of Hierarchical Decision Model (HDM). Paper presented at the 2023 Portland International Conference on Management of Engineering and Technology (PICMET).
  10. Kristamuljana, S. (1998). Landasan Teori Metode Kasus untuk Pengembangan Manajer yang Rasional. Paper presented at the Forum Manajemen.
  11. Kurnia, G., Johanes, H., Hidayat, D., Rozha, A., Zahvira, M., & Sukarno, I. (2020). Improving Airport On-Time Performance Using Kepner-Tregoe Problem-Solving Approaches. Jurnal Teknologia, 3(1), 493086.
  12. Luft, J. A., Jeong, S., Idsardi, R., & Gardner, G. (2022). Literature reviews, theoretical frameworks, and conceptual frameworks: An introduction for new biology education researchers. CBE—Life Sciences Education, 21(3), rm33. doi:https://doi.org/10.1187/cbe.21-05-0134
  13. Mahgoub, M., Hussein, M., & Mousa, A. (2024). Extended discharge time of ready-mixed concrete: Myth or necessity? Construction and Building Materials, 437, 136913. doi:https://doi.org/10.1016/j.conbuildmat.2024.136913
  14. Mann, W. C., & Lane, J., P. (1995). Technology and Disability. 4(2).
  15. Nson, Y. D. (2024). Management by walking about in achieving organizational excellence: The role of total quality management. Annals of Human Resource Management Research, 4(2), 111-126. doi:https://doi.org/10.35912/ahrmr.v4i2.2408
  16. Nurokhman, N., Suharyanto, I., & Rochmawati, U. (2021). Evaluasi Mutu Beton Dari Berbagai Ready Mix Pada Gedung Parkir Yogyakarta International Airport. CivETech, 3(2), 55-65. doi:https://doi.org/10.47200/civetech.v3i2.1058
  17. Padmowati, R. d. L. E. (2009). Pengukuran index konsistensi dalam proses pengambilan keputusan menggunakan metode AHP. Paper presented at the Seminar Nasional Informatika (SEMNASIF).
  18. Palcic, I., & Lalic, B. (2009). Analytical Hierarchy Process as a tool for selecting and evaluating projects. International Journal of Simulation Modelling (IJSIMM), 8(1). doi:https://doi.org/10.2507/IJSIMM08(1)2.112
  19. Pottonen, J. (2023). Utilization of The 8d Quality Tool in Solving The Quality Problems in John Crane Nordic Units.
  20. Quesada, H., Gazo, R., & Sanchez, S. (2012). Critical factors affecting supply chain management: A case study in the US pallet industry. Pathways to supply chain excellence, 33-56.
  21. Ravitch, S. M., & Riggan, M. (2016). Reason & rigor: How conceptual frameworks guide research: Sage publications.
  22. Saaty, T. L., & Vargas, L. G. (2012). Models, methods, concepts & applications of the analytic hierarchy process (Vol. 175): Springer Science & Business Media.
  23. Sabbaghi, A., & Vaidyanathan, G. (2004). SWOT analysis and theory of constraint in information technology projects. Information systems education journal, 2(23), 1-19.
  24. Simchi-Levi, D., Kaminsky, P., & Simchi-Levi, E. (2004). Managing the supply chain: the definitive guide for the business professional: McGraw-Hill.
  25. Stemmler, L. (2002). The role of finance in supply chain management. Paper presented at the Cost management in supply chains.
  26. Steward, M. D., Wu, Z., & Hartley, J. L. (2010). Exploring supply managers' intrapreneurial ability and relationship quality. Journal of Business-to-Business Marketing, 17(2), 127-148. doi:https://doi.org/10.1080/10517120903407857
  27. Westland, J. (2006). The project management life cycle: a complete step-by-step methodology for initiating, planning, executing & closing a project successfully: Kogan Page Limited.